Construction and installation of metal mesh

  1. When installing the metal mesh rope mesh on the exterior curtain wall, you must first install the mesh pendants and supports. When the metal mesh length is >5m, wind braces must be added.
    Fixing method: Pull out a few horizontal stainless steel round rods at the top of the metal mesh, pass a steel rod through the middle of the wire rope, and hang it on the installed pendant.
    The lower end of the metal mesh is also threaded through a steel rod, and is tightened downward with a high-strength tension spring or set of rods, and then fixed to the supporting connector.
  2. When installing the conveyor belt, you can drill holes in the upper and lower steel pipes with the same pitch. After placing the conveyor belt into the holes, insert a steel rod to complete the connection and tighten it up and down.
    Another way is to pass a steel rod through the upper and lower ends, then connect it to the pendant with a lifting ring with the same pitch, and tighten it up and down.
  3. Screen installation
    First, make the large frame of the screen. After welding and polishing 45° to 45° angles, weld the first frame of the screen.Secondly, lines are printed after deepening the original design, and the pattern is divided into sections of curves according to the width of the mesh. The mesh is cut into pattern shapes and then sent to the site for installation.Then weld the second layer and third layer frame of the screen, and finally complete the installation of the second layer of mountain-shaped mesh and the fourth layer of frame.
  4. When installing the metal partition net, connect a flat spring with the same pitch to the upper and lower ends of the metal net, then connect the flat spring to the flat steel with the same pitch hole, and tighten the upper and lower flat steel to achieve tension. To achieve the effect of metal mesh, just fix the flat steel up and down in order.
  5. When installing the curtain, reserve a good space according to the size. Install the metal chain and pulleys on the upper end of the curtain in sequence. The distance between the pulleys is 15~20cm. After fixing the track to the ceiling, insert the pulleys in sequence.
  6. When installing the stretch mesh ceiling, first install the keel according to the elevation required by the drawing, adjust the straightness left and right with the laser line, and then use self-drilling screws to fix the keel and the ear pieces on the frame together.
  7. When installing the stretch mesh ceiling, first install the keel according to the elevation required by the drawing, adjust the straightness left and right with the laser line, and then use self-drilling screws to fix the keel and the ear pieces on the frame together. After that, slowly tighten the diamond-shaped mesh to a 60-degree angle, which is the ideal tension level, and then reinforce the surrounding frames or stainless steel cables and other accessories.